Establishing of LEDIB Cluster House Project is a business development project consisting of the small-scale construction works, interior design and staff recruitment. The project management was enabled through application of the basic concept implemented in 6 stages: Project Objective and Description; Identification of the Project Manager and Team; Project Implementation Timeline Planning; Identification of the Required Resources and Finances; Implementation Monitoring and Necessary Interventions and Project Closeout. The basic objective of the Project is the closeout (completion) in the shortest period of time and with the lowest expenses. Planning, monitoring and control of the project implementation rely on the software support of the Microsoft Project – the standard program for project management.
Table 3 Defining the key events (milestones) of the project Nr Milestones Target date. (n.d.).
Project approval and project team forming 01. (2011). 2.
Defining the detailed activity plan. (n.d.).
Beginning of an architect’s services 02. (2011). 2.
Ending of an architect’s services 22. (2011). 2.
Beginning of activity plan implementation monitoring 03. (2011). 2.
Ending of activity plan implementation monitoring 28. (2011). 2.
Beginning of the stage of selection of service provider for small-scale construction works and interior design 03. (2011).
Ending of the stage of selection of service provider for small-scale construction works and interior design 07. (2011).
Beginning of stage -electric works 08. (2011). 2.
Ending of stage -electric works 10. (2011). 2.
Beginning of stage -painting works 10. (2011). 2.
Ending of stage -painting works 17. (2011). 2.
Beginning of stage -locksmithing works 21. (n.d.).
Ending of stage -locksmithing works 22. (2011). 2.
Beginning of stage -equipping with furniture 08. (2011). 2.
Ending of stage -equipping with furniture 20. (2011). 2.
Beginning of stage -chandeliers setting up 18. (n.d.).
Ending of stage -chandeliers setting up 19. (2011). 2.
Beginning of stage -curtains setting up 20. (2011). 2.
Ending of stage -curtains setting up 21. (2011). 2.
Beginning of stage -paintings setting up 22. (2011). 2.
Ending of stage -paintings setting up 22. (2011). 2.
Beginning of stage -floral arrangements setting up 22. (2011). 2.
Ending of stage -floral arrangements setting up 22. (2011). 2.
Beginning of stage -carpets setting up 22. (2011). 2.
Ending of stage -carpets setting up 22. (2011). 2.
Beginning of stage -staff recruitment 01. (2011). 2.
Ending of stage -staff recruitment 22. (2011). 2.
Beginning of telecom. and IT equipment installing 22. (2011). 2.
Ending of telecom. and IT equipment installing 22. (2011). 2.
Beginning of probationary work 23. (2011). 2.
Table 3 contains data that are the base for MS Project operations. (2011).
Mrežno Planiranje I Ms, Project, Stanimirović, P., & Jovanović, I. (2008).
Upravljanje, Jovanović, P., & Grafoslog. (2002).
Upravljanje, & Jovanović, P. (2006).
Brzi vodič MS Project 2003, Petronijević, P, Građevinski fakultete Univerziteta u Beogradu, Katedra za menadžment, tehnologiju i informatiku u građevinarstvu. (2006).
Uspostavljanje i razvoj LEDIB Kuće klastera" LEDIB program, Nišavski okrug. (2010).
The statements, opinions and data contained in the journal are solely those of the individual authors and contributors and not of the publisher and the editor(s). We stay neutral with regard to jurisdictional claims in published maps and institutional affiliations.